The YCW contracts (2011) require the contractor to provide two copies of the “master programme” to the architect/contract manager. However, the master`s degree does not appear in the list of contractual documents and YCW specifies that it does not contract the obligations of the contractor. As a result, the only binding date for the contractor is the completion date and the contractor has until the last date of the day to complete the work. If the programme is binding, the contractor is not alone in assuming additional responsibilities. . . .